[Note - Checklists and the Gantt are available on the MyConstruct Standard, Pro and Studio plans]
Build a checklist for each kind of job you do (a single storey, a two storey, a renovation) and reuse it on every job. You don't need a checklist per job: add the standard one and adjust it on the job.
Our example (all names and details are made up): the checklist Construction Schedule - 2 Storey has 37 tasks from site cut to handover. It runs on job #2041, 17 Banjo Street, a two storey home for Mia and Josh. Sam, the site supervisor, runs the schedule and calls up the trades.
On this page
- Open Manage Checklists
- Start a checklist
- Add your tasks
- Trades who work on the same day
- Hold points, important tasks and notifications
- Reorder and tidy up
- Checklist settings
- Questions and tips
Open Manage Checklists
Go to Tasks → Manage Checklists.
- Create Checklist starts a new checklist.
- Click a checklist to show its tasks below.
- Edit renames the checklist and sets when it's added to jobs. The arrow beside it has more options (see Checklist settings).
- Create Task adds a task.
- Each task's Days Start (Start After # Days), Duration, Dependency, who it's assigned to, and whether it shows on the job's Gantt and the Business Gantt. Hover over Days Start for a reminder of how it's counted.
Start a checklist
Click Create Checklist, give it a name (for example Construction Schedule - 2 Storey) and click Create. It appears in the list; click it to start adding tasks.
The arrow on Create Checklist (1) offers MyConstruct Templates (2): ready-made lists such as Tender Requirements, Construction Requirements, Maintenance Period and a Supervisor Checklist. Click one to copy it into your checklists, then add durations, dependencies and trades to suit your business.
Templates are a starting point. A template copies the task names only, each one day long with no dependency. Clicking a template twice makes two copies, so check the list before you click again.
Add your tasks
Select the checklist, then click Create Task (or Edit on a task). Add the tasks in the order they happen. Here's Plumber - Rough in, which follows the frame inspection:
- Task Name: what the trade or step is. Starting with the trade (Plumber, Electrician) makes call-ups easy to read.
- Colour: the bar colour on the Gantt. Many builders give each trade its own colour.
- Duration: working days the task takes.
- Dependency: the task it waits for. Leave it as None for the first task.
- Start After # Days: extra days to wait after the dependency finishes. 0 means the next working day.
- Auto Assign: who the task goes to on every job. Pick a supplier or staff member, or a job role such as Job: Supervisor, which becomes whoever is the supervisor on each job. For a supplier, tick which of their email addresses get the call-ups.
- Show in Job Gantt and Show in Business Gantt: turn on the Business Gantt for the milestones you want to see across all jobs (see The Business Gantt and schedules in the portals).
Click Create (or Update when editing). The task appears in the list.
Trades who work on the same day
In our checklist, the windows, external doors and the lock-up carpenter all start the day after the roof goes on, and the plumber, electrician and air conditioning installer all start the day after the frame inspection.
- Three tasks share the dependency Roofer - Roof on, so they all land on the same day.
- Three rough-in trades share Frame inspection, so they all start the next working day after it.
- Their Days Start is 0: no extra wait.
Insulation, on the other hand, follows Plumber - Rough in, because the insulators need the pipes in first. That's what a link is for. There's more on this in Job scheduling using Checklists and Gantts.
Hold points, important tasks and notifications
These are further down the same task form.
- Show in Business Gantt: on for the frame inspection, so it shows on the company-wide Gantt.
- Hold Point: the task can't be ticked complete until its Hold Type is met: a photo, an electronic signature or a completed form. Use it for inspections and sign-offs. (Form hold points use MyC Docs forms, which are on the Studio plan. See Building forms in MyC Docs.)
- Mark as Important: the task shows in bold on the job so it stands out.
- Notify on Complete: emails the people you pick (or any addresses you type) a few minutes after the task is ticked complete. Leave both empty to notify whoever the task is assigned to. Handy for "slab poured" or "practical completion".
- Purchase Order Mapping (Pro and Studio plans, with Estimating): the cost centres the task covers, so the matching purchase order is linked to the task when the checklist is added to a job. See Linking purchase orders to checklists.
In the task list, a lock marks a hold point, a star an important task and a bell a notify on complete.
Reorder and tidy up
- Drag the ≡ handle at the start of a row to move a task. If you move a task above the task it depends on, its dependency is cleared and you'll be asked to set it again.
- Edit changes a task; the arrow beside it deletes it.
- The List / Visual switch above the tasks shows the checklist as a timeline on a preview calendar, where you can drag bars and draw links. The switch only appears when the Gantt engine is Pro. Weekends and holidays are applied when the checklist is added to a job.
Checklist settings
Click Edit on a checklist (and the arrow beside it for more).
Name (1) renames the checklist. Add to jobs (2) adds the checklist to a job automatically when the job's status changes to the status you pick (for example Active), starting that day. It's only added once, so moving a job back and forth between statuses doesn't add it twice. Leave it as Only when added by hand to add it yourself. Job statuses are set up in Manage Jobs View and Custom Status options.
- Edit: the settings above.
- Visibility: show the checklist to all staff, or only to staff in certain job roles (for staff who can only see their own jobs).
- Archive: stop offering the checklist for new jobs. Jobs already using it keep it. Show archived checklists under the list brings it back.
- Delete: only for checklists no job uses. If one does, you'll be told which jobs, and you can archive it instead.
- Export to CSV and Export Project XML (6): download the tasks for a spreadsheet or Microsoft Project.
Importing a checklist from CSV is available through MyConstruct support.
Franchisors also see Share, to share a checklist with all franchisees. See Multiple businesses or franchise logins.
Questions and tips
I changed the checklist but my jobs didn't change.
Each job has its own copy. Changes here apply to jobs you add the checklist to from then on. Change a job's tasks on the job itself.
I clicked a template and now I have two of them.
Each click makes a copy. Delete the extra one with the arrow beside Edit.
Why can't I delete a checklist?
A job is using it. Archive it instead, so it's no longer offered for new jobs.
Need a hand? Contact our support team.