[Note - Checklists and the Gantt are available on the MyConstruct Standard, Pro and Studio plans]
Add a checklist to a job and every task gets its dates. Then use the job's Checklists tab to tick work off, see where each call-up is up to and keep the schedule moving.
Our example (all names and details are made up): the checklist Construction Schedule - 2 Storey has 37 tasks from site cut to handover. It runs on job #2041, 17 Banjo Street, a two storey home for Mia and Josh. Sam, the site supervisor, runs the schedule and calls up the trades.
On this page
- Add a checklist to a job
- Choose the start date and days off
- Your job's schedule
- Read a task
- Tick work off and change dates
- Complete a hold point
- Change who a task is assigned to
- Questions and tips
Add a checklist to a job
Open the job, go to the Checklists tab and click Add Checklist. Sam adds Construction Schedule - 2 Storey to job #2041 when the site is ready.
- Add Checklist lists your checklists.
- Print Checklists: a PDF of every checklist on the job.
- From Estimate...: build a checklist from the estimate's supplier orders, one task per order with its delivery date (Pro and Studio plans, with Estimating).
- Purchase Orders...: open the job's purchase orders screen to review and edit task links (Pro and Studio plans, with Estimating; see Managing linked purchase orders on a job and Gantt).
- Pick the checklist to add. Archived and empty checklists aren't listed, and a checklist already on the job can't be added again.
A checklist can also be added automatically when the job's status changes. See Checklist settings in Building a checklist.
Choose the start date and days off
- Start date: the day the first task starts. Every other date is worked out from it.
- Treat all Saturdays / Sundays as off-days: untick one if your trades work that day. If your business always takes weekends off (set in Business details), both stay ticked.
Click Add. Public holidays for your business's country and state, and off-days in your business calendar, are skipped automatically. If the checklist maps purchase orders, you'll also pick the estimate to match them against (Pro and Studio plans, with Estimating; see Linking purchase orders to checklists).
Your job's schedule
The job's Checklists tab now shows the checklist and its tasks.
- The checklists on this job, with when they started and their last due date. Click one to see its tasks; drag the ≡ handle to reorder them. (Complete) appears when every task is done or N/A.
- Print makes a PDF of this checklist. The arrow has Visibility and Remove (removing a checklist also removes it from the Gantt).
- Order: list the tasks in checklist order, by start date or by due date.
- Options: Add Task to this job only, and Select for Email to call up several trades at once (see Calling up trades from a checklist).
The job has its own copy. Changes on the job (dates, extra tasks, a different trade) only affect this job. Changes to the checklist in Manage Checklists only affect jobs you add it to from then on.
Read a task
It's Wednesday 25/11. Here are the next few tasks on job #2041, each showing where its call-up is up to.
- Green dot: the trade accepted the call-up (or you confirmed by phone). Hover over it to see when.
- Orange dot: waiting for an answer, or the trade has asked for different dates. Hover over it to see which. While you're waiting, the tooltip says Pending. After a trade proposes dates, it says Date change requested on {d/m/Y h:i a} - proposed start {d/m/Y}, due {d/m/Y}.
- A started task shows how long it has been running.
- Until a task is ticked, its dates are the plan (Projected Start Date / Projected End Date).
- Called: confirmed by phone.
- A lock: a hold point. Bold text is an important task.
- Red dot: the trade declined. Reassign the task or call them.
- Email sends the call-up. After sending it becomes Resend; while a batch is going out it shows Queued. The date beside it is when it was last sent.
- Recalculate Dates re-works the dates for the off-day settings above it. Ticking the Saturday / Sunday boxes only saves the setting; dates change when you click Recalculate Dates.
Under each name you'll see Assigned to (click it to change who) and Dependent on, the task it follows.
Tick work off and change dates
| STARTED | Tick when work starts. Today is filled in; change the date if it started another day. |
| COMPLETED | Tick when it's done (you can't complete a task that hasn't started). A hold point asks for its photo, signature or form first. |
| DUE | Change the due date for a quick fix. To move a task and everything after it (skipping days off), drag it in the Gantt instead. See Using the job Gantt chart. |
| N/A | For a task this job doesn't need. Later tasks move earlier by its length and its links are removed, so it's best done before work starts. |
The arrow beside Email / Resend has Mark as called (1), Todo (2) for a quick to-do on the task, and Edit (3) to change the task's name, timing, hold point and linked purchase orders (see Managing linked purchase orders on a job and Gantt). Delete appears there once a task is N/A.
Complete a hold point
The frame inspection needs a signature. When Sam ticks it complete, MyConstruct asks for it first:
- Sign in the box (with a finger on a phone or tablet).
- Type the signer's full name, and their email if you want.
- Tick the declaration and click Save Signature. The task is then completed.
A photo hold point asks for a photo instead, and a form hold point opens the form to fill in.
Change who a task is assigned to
Click the name after Assigned to:.
- Reassign To: pick one or more staff or suppliers. Type to search.
- Tick which of the supplier's email addresses get the call-up.
- Email Task: Alert Staff via Email sends the new assignee a quick alert now (suppliers too). No Alert just saves.
If the task was already emailed to someone you're removing, you'll be asked whether to send them a cancellation. Reassigning the task doesn't move its linked purchase order: on Pro and Studio plans with Estimating, see Purchase orders on call-ups and changing supplier to move the order too. Suppliers and their contacts are set up in Contacts and Groups.
Questions and tips
I can't tick a task complete.
Tick Started first. If it has a lock, it's a hold point: add the photo, signature or form when asked.
I ticked Saturday as an off-day but nothing moved.
Ticking the box only saves the setting. Click Recalculate Dates to re-work the dates.
How do I delete a task on a job?
Tick N/A first; Delete then appears in the arrow menu beside Email.
Can I add a task just for this job?
Yes: Options → Add Task. It's only added to this job, not the checklist.
Need a hand? Contact our support team.