[Note - linking purchase orders to checklist tasks is available on the MyConstruct Pro and Studio plans, with Estimating]
A task on your schedule is the when; a purchase order is the what and who. Linking them means each task shows whether its order has gone out and been confirmed, and a call-up can show the trade exactly what has been ordered.
Linking orders to tasks needs Estimating (the orders come from your estimates) and a checklist on the job. To map checklist templates in Tasks → Manage Checklists you need Tasks / Checklists set to Read / Write / Delete Access in Manage Staff Accounts. On a job, you can see linked orders with Tasks / Checklists set to Read Access or higher, and you can change links with Read / Write Access or higher, plus Estimating on the plan. Mark as Cancelled and Set Supplier are for account owners and staff with full Estimates access. The basics of checklists and scheduling are in Job scheduling using Checklists and Gantts, and raising and sending orders is in Sending and managing Purchase Orders.
Example job #2052, 21 Bottlebrush Way (two storey home): Sam runs Construction Schedule - 2 Storey against Contract estimate (nine trade cost centres from TR-110 Concrete to TR-190 Plastering). The names and orders are examples.
On this page
- Words you'll see
- Order status on a task
- Pick the Type of Work and see the mapping
- Map a task
- Choose the estimate when adding a checklist
- Pick the order where there's a choice
- Questions and tips
Words you'll see
| Cost centre | A trade or section of your estimate, such as TR-110 Concrete. Orders are raised per cost centre. |
| Delivery | One supplier's order for a cost centre. A cost centre can be split into Delivery 1, Delivery 2 and so on (D1, D2), for example the footings pour and the slab pour. |
| Overrun | An extra order for a cost centre after the main ones (O1, O2), for example top-up concrete. |
| PO number | Job number / cost centre code, then the order's level: 2052/TR-110.2. |
| Link | Ties a task to one delivery, or to All deliveries of a cost centre (for one supplier, or all of them), including deliveries raised later. |
| Estimate | The estimate the orders come from. A job with several estimates (a contract and a variation, say) can link tasks to orders on any of them. |
These nine labels are what a task shows. In Manage Orders, the same work is listed as Ready to Send (not yet sent), In Send Queue or Sent. There is no Cancelled status: Mark as Cancelled resets a Sent order to Ready to Send in the list and Not ordered on the task.
A link points at the delivery (estimate, cost centre, supplier and delivery number), not at a PO number. So if the order is re-sent or renumbered, the task stays linked to it. If the delivery moves to another supplier, it's a different delivery, so you link the task again (see Purchase orders on call-ups and changing supplier).
Order status on a task
Wherever a task shows its orders, it uses the same coloured labels. A task with several orders shows the one that needs attention most, with a count beside the cart.
| Label | What it means |
|---|---|
| Not ordered | The order is on the estimate but hasn't been sent or marked as ordered. |
| Queued | The order is queued to be sent, but hasn't gone to the supplier yet. |
| Sent | The order has gone to the supplier, without asking them to confirm. |
| Awaiting confirmation | The order was sent with Request confirmation and the supplier hasn't answered yet. |
| Confirmed | The supplier accepted the order. |
| Declined | The supplier declined the order. Ring them, or change supplier (see Purchase orders on call-ups and changing supplier). |
| Partly ordered | An All deliveries link where some deliveries are ordered and some aren't yet. |
| No orders yet | The link is there but there's nothing on the estimate for it yet. It fills in by itself when the order is raised. |
| Order changed | The delivery is no longer on the estimate (deleted, or moved to another supplier). Remove the link and link the current order. |
Pick the Type of Work and see the mapping
Tell each task on your checklist which cost centre it covers. You do this once in Tasks → Manage Checklists (see Building a checklist), and every job you add it to links itself.
- Type of Work: the cost centre list (the same one your estimates use; see Manage Cost Centres) that this checklist maps to. Choose it before mapping tasks.
- A blue tag under a task shows the cost centre it covers. Here both concrete tasks cover TR-110 Concrete: the piers and footings use Delivery 1 and the slab pour uses Delivery 2 (you'll pick those on the job).
- A green truck shows a task's allocated supplier. Windows - Delivery takes Clearview's order from TR-140 Windows & Doors, while External doors - Delivery takes whichever order is left.
Tasks with no tag, like the site cut and the carpenter, aren't linked to an order. That's fine: not every task has a purchase order.
Map a task
At the bottom of Create Task and Edit Task is Purchase Order Mapping:
- Cost Centres: the cost centre (or several) this task covers. Used to find the matching order when the checklist is added to a job.
- Allocate Supplier: optional. When a cost centre is split between suppliers (windows from Clearview Windows, doors from Doorway Co), pick the supplier this task is for. The hint lists the cost centre's default suppliers; leave it blank to match any of them.
- Link matching purchase orders automatically: untick it to map the task but leave linking to you.
Map a cost centre to every task that needs it: a delivery task and an install task can both cover TR-180 Kitchen. On the job each one shows the same order.
Choose the estimate when adding a checklist
When you add a mapped checklist on a job's Checklists tab (see Adding a checklist to a job and working it day to day), MyConstruct looks at the job's estimate and links each task to the orders for its cost centre.
Under the start date and weekend options is Match purchase orders against estimate (1). If the job has one estimate it's picked for you; with several, choose the one whose orders the schedule should follow (usually the contract estimate). Click Add.
Each mapped task is then linked like this:
- One supplier on the cost centre: the task is linked to All deliveries of that supplier, so later deliveries and overruns are covered too.
- An allocated supplier: the task takes that supplier's orders.
- Several suppliers and no allocation: you're asked which order next.
- No orders yet for the cost centre: the task waits, and links itself the moment an order is sent or marked as ordered.
Pick the order where there's a choice
If a mapped task has more than one matching order and no allocated supplier, Match Purchase Orders opens before the checklist is added:
- The summary says how many tasks need you; 9 tasks matched automatically opens the list of the rest.
- External doors - Delivery covers TR-140 Windows & Doors, which has 2 possible orders (Clearview Windows and Doorway Co).
- Pick the order, or Leave unlinked to sort it out later.
- Apply Checklist adds the checklist with your choices.
Cancel on this window doesn't add the checklist at all. To add it and decide about the order later, choose Leave unlinked and click Apply Checklist.
Questions and tips
A task says No orders yet - is it broken?
Not if the order just hasn't been raised. When an order for that cost centre is sent or marked as ordered, waiting tasks link to it by themselves.
I clicked Cancel on Match Purchase Orders and my checklist isn't on the job.
Cancel there doesn't add the checklist. Add it again and choose Leave unlinked for anything you're not sure about.
Need a hand? Contact our support team.
Comments
0 comments
Article is closed for comments.