[Note - linking purchase orders to checklist tasks is available on the MyConstruct Pro and Studio plans, with Estimating]
A call-up books the trade for the task's dates. The purchase order is what they're supplying. Put the order summary in the call-up so the trade sees both in one place, and if a supplier declines or changes, follow the three steps below to keep the task, the order and the link in step.
Send the purchase order from the estimate's Orders tab as usual (see Sending and managing Purchase Orders; the task's label tells you if it's gone). The call-up can show the order, but it doesn't send, re-send or confirm it. A trade accepting the call-up confirms the date; confirming the order is done from the order email.
Example job #2052, 21 Bottlebrush Way (two storey home): Sam runs Construction Schedule - 2 Storey against Contract estimate (nine trade cost centres from TR-110 Concrete to TR-190 Plastering). The names and orders are examples.
On this page
- Include the order summary in a call-up
- What the trade sees on the Order tab
- Changing supplier
- 1. Reassign the task and cancel the old call-up
- 2. Cancel the old order and give it to the new supplier
- 3. Spot the old link, link the new order and call up
- Questions and tips
- Quick reference
Include the order summary in a call-up
When emailing a trade from the Checklists tab (see Calling up trades from a checklist), open the confirmation options:
- Tick Include order summary section to add an Order tab to the trade's confirm page.
- Pick the estimate and order to show. For tasks linked from the checklist, the task's order is picked for you: here Clearview Windows' order. For links you added by hand, choose it from the list.
- The order summary is part of the confirm page, so Ask recipient to confirm must be ticked.
What the trade sees on the Order tab
- The Order tab under Details shows the order number, order date, supplier and job...
- ...the delivery and its date, then every line with quantities, unit prices and totals for that supplier's lines. If the order doesn't have a PO number yet, the tab shows an internal id instead.
- The trade accepts, declines or proposes another date for the task as usual.
When Include order summary section is ticked, the Order tab always shows those unit prices and totals.
When you call up several trades at once with Batch send or Send as group, each call-up uses its own task's order. See Calling up trades from a checklist.
Changing supplier
In our example, CoolBreeze Air declined both the call-up and the order for the air conditioning rough-in, so Sam moves the work to ArcticFlow Air. That's three things to change: who the task is assigned to, who the order is with, and which order the task is linked to.
1. Reassign the task and cancel the old call-up
Click the supplier name beside Assigned to: on the Checklists tab.
Pick the new supplier in Reassign To (type to search) and tick which of their contacts get call-ups (2). Click Reassign Task.
Because CoolBreeze Air was already called up, MyConstruct asks whether to tell them. Yes, send cancellation (1) emails them a Work cancelled notice with a cancelled copy of the linked order. Either way, their confirm link stops working and the task is ready to call up ArcticFlow Air.
Reassigning the task doesn't touch the purchase order: it's still CoolBreeze Air's, still on the estimate and still in your accounts. The next step moves it.
2. Cancel the old order and give it to the new supplier
Mark as Cancelled and Set Supplier are for account owners and staff with full Estimates access. Open the job's Orders tab or Manage Orders (see Sending and managing Purchase Orders), then open the arrow beside View on that order's row. The two actions never show together: Mark as Cancelled is only offered on Sent orders; Set Supplier is only offered once the order is Ready to Send. Multi Select offers Set Supplier only.
On the Sent order, choose Mark as Cancelled:
MyConstruct asks whether to email the supplier a cancelled copy of the order. Sam already sent one when reassigning the task, so he picks No, just cancel (1). If you didn't send a cancellation on the task, choose Yes, send cancellation here. There is no Cancelled status: the order resets to Ready to Send in the list and Not ordered on the task. The old supplier's confirm link stops working, and the task's link stays.
Open the arrow beside View again on the now Ready to Send row and choose Set Supplier:
Choose the new supplier (1) and click Set Supplier. Check the prices with Edit Order if the new supplier's quote is different, then Send Order as usual, with Request confirmation ticked if you want ArcticFlow Air to confirm it.
A sent order keeps its supplier: cancel it first so it returns to Ready to Send, then use Set Supplier.
3. Spot the old link, link the new order and call up
Open Add Checklist → Purchase Orders... on the job's Checklists tab and pick the task:
- The task is still linked to All deliveries of TR-170 from CoolBreeze Air, which now has no orders yet.
- ArcticFlow Air's order, sent and awaiting confirmation, isn't linked to anything.
- All deliveries is offered again because the old link doesn't cover ArcticFlow Air.
Remove the old link with its ×, tick ArcticFlow Air's order and click Link (or All deliveries):
The task now shows ArcticFlow Air's order (1), Awaiting confirmation (2), and the summary no longer counts an order that isn't on any task. Finally, call up ArcticFlow Air from the Checklists tab with the order summary included.
Questions and tips
Does sending a call-up also send the purchase order?
No. Send the order from the estimate's Orders tab. The call-up can include a summary of it.
When a trade accepts the call-up, is the purchase order confirmed too?
The call-up and the order are confirmed separately: accepting the call-up confirms the date. The order is confirmed from the order email's own link.
Why didn't reassigning a task change its purchase order?
The task and the order are separate, so you stay in control of what's in your accounts. On the Sent order, choose Mark as Cancelled from the arrow beside View, then Set Supplier once it's Ready to Send, send the new order and link it again. The task's old link stays until you remove it.
Is there a Cancelled order status?
No. Mark as Cancelled is only offered on Sent orders. It resets the order to Ready to Send in Manage Orders and Not ordered on the task. The old supplier's confirm link stops working, and the task link stays.
Quick reference
- Map once: Tasks → Manage Checklists → set Type of Work → edit each task → Cost Centres (and Allocate Supplier for split cost centres).
- Add to a job: Add Checklist → choose the estimate → pick orders where asked, or Leave unlinked.
- Manage on the job: check labels on the Checklists tab; use Add Checklist → Purchase Orders... to fix links and accept suggestions.
- Delivery links: One delivery for split work (footings, slab); All deliveries for one task covering the whole trade (later orders included). Links survive re-sends, not supplier changes.
- Where changes save: Checklists tab saves at once; the Gantt task editor saves on Save.
- Change supplier: Reassign the task (Yes, send cancellation) → on the Sent order, open the arrow beside View and choose Mark as Cancelled (No, just cancel) → on the now Ready to Send row, open the arrow beside View and choose Set Supplier → Send Order → Purchase Orders... → × old link → Link the new order → call up the new supplier.
Need a hand? Contact our support team.