[Note - linking purchase orders to checklist tasks is available on the MyConstruct Pro and Studio plans, with Estimating]
Once a checklist is on a job, you can read every task's order status right on the Checklists tab, narrow split deliveries or change links, review everything on the job's Purchase orders on this job screen, and check or edit links from the Scheduling tab (Gantt).
Example job #2052, 21 Bottlebrush Way (two storey home): Sam runs Construction Schedule - 2 Storey against Contract estimate (nine trade cost centres from TR-110 Concrete to TR-190 Plastering). The names and orders are examples.
On this page
- Read the order labels on the Checklists tab
- See and change a task's orders
- Link one delivery vs All deliveries
- Purchase orders on this job
- Link orders to a task on the job screen
- Deliveries, overruns and shared orders
- The POs column in the Gantt
- The Purchase Orders tab in the Gantt
- Questions and tips
Read the order labels on the Checklists tab
The job's Checklists tab shows each task's order status beside its dependency, so you can see at a glance what's ready before you call a trade.
- The frame order is Awaiting confirmation: sent, but Hardwood Hub Timber hasn't confirmed it.
- The roof order is Confirmed.
- The windows order is waiting for Clearview Windows to confirm.
- The doors order was Sent without asking for confirmation.
- The electrical order is on the estimate but Not ordered yet: send it before you call up the electrician.
- CoolBreeze Air Declined the air conditioning order (the red dot by their name says they also declined the call-up). See Purchase orders on call-ups and changing supplier to move the work to another supplier.
- The plastering link has No orders yet: the order will link itself when it's raised.
See and change a task's orders
Click the arrow beside Email / Resend on a task and choose Edit, then scroll to Purchase Orders. Here's Concretor - Piers & footings straight after the checklist was added:
- The task's link: All deliveries of TR-110 Concrete from Solid Base Concreting, 3 orders, one not ordered yet. TEMPLATE says it came from the checklist. The × removes the link.
- Search by cost centre, supplier or PO number.
- Filters: This task's cost centres, orders Not on any task, and Show not ordered to include deliveries that haven't been sent.
- Each delivery with its PO number, status, supplier, delivery number, order date and value. Also linked to names other tasks that share it.
- All deliveries linked: this task covers the whole cost centre for that supplier.
Link one delivery vs All deliveries
The piers and footings only need Delivery 1, though; the slab pour takes Delivery 2 and the overrun. Removing the All deliveries link and ticking Delivery 1 narrows it down:
- The task is now linked to PO #2052/TR-110.1, Delivery 1, only.
- Tick one or more deliveries and click Link (it says Link 2 deliveries when you tick two).
- All deliveries links the whole cost centre again, including deliveries raised later.
Use one delivery when a trade's work is split across visits (footings, then slab). Use All deliveries when one task covers everything for that trade (plastering, the kitchen), so top-ups and overruns are covered without you linking them.
Changes in this panel are saved as you make them.
Purchase orders on this job
Click Add Checklist → Purchase Orders... on the job's Checklists tab for one screen with every task and every order on the job: see what's linked, spot orders nobody has picked up and fix links in bulk.
- The summary: tasks, tasks with orders, tasks waiting for orders, orders on the estimates, and raised orders not on any task (worth a look: they're sent but no task tracks them).
- Suggested links: orders MyConstruct thinks belong to a task, with the reason. Untick any you don't want and click Link selected.
- Why it's suggested: here the task name matches the cost centre. Other reasons are From the checklist template and This task was created from this order (for tasks built with Add Checklist → From Estimate...; see Adding a checklist to a job and working it day to day).
- Show All tasks, those Waiting for orders, those with No orders or those With orders. Each task shows its order status.
- With no task picked, the right side lists every order on the job and which task it's linked to.
Link orders to a task on the job screen
Click a task on the left to inspect and change its links:
- The task's links. Windows - Delivery has Clearview Windows' deliveries of TR-140 Windows & Doors.
- The same search and filters as in Edit Task.
- All deliveries linked for Clearview Windows. Doorway Co's order in the same cost centre isn't part of this link.
- Doorway Co's order is linked to External doors - Delivery instead.
- Tick deliveries and click Link.
The dates beside each order are the date it was ordered. The delivery date is on the order itself and on the call-up's order summary (see Purchase orders on call-ups and changing supplier).
Deliveries, overruns and shared orders
How our example's orders are spread across its tasks:
| Task | Linked to | Why |
|---|---|---|
| Concretor - Piers & footings | TR-110 Delivery 1 | The first pour only. |
| Concretor - Slab pour | TR-110 Delivery 2 and Overrun 1 | The slab, plus the top-up for the slab. |
| Frame & trusses - Delivery | All deliveries, TR-120 | Frames and trusses arrive in two drops; one task tracks both. |
| Windows - Delivery | All deliveries, TR-140, Clearview Windows | Allocated supplier on the checklist. |
| External doors - Delivery | TR-140 Delivery 1, Doorway Co | Picked in Match Purchase Orders. |
| Plumber - Rough in | All deliveries, TR-150, Flowright Plumbing | Allocated supplier. The plumbing supplies order from Pipeline Plumbing Supplies in the same cost centre isn't part of this link. |
| Kitchen - Install | All deliveries, TR-180 | Accepted from Suggested links. |
- An order can be linked to more than one task (a delivery task and an install task). Each shows it, with Also linked to.
- A task can have orders from several cost centres, for example a lock-up task with windows and doors.
- An order that's re-sent keeps its links: the task shows the new PO number and status.
The POs column in the Gantt
The job's Scheduling tab (see Using the job Gantt chart) shows the same links, so you can check orders while you're moving dates.
The POs column (1) counts each task's linked orders; the slab pour (2) has two. Hover over a task's bar and the tooltip lists its orders with their status. Without Estimating the column still appears, but it stays empty. Purchase Order Mapping and Add Checklist → Purchase Orders... are hidden without Estimating.
The Purchase Orders tab in the Gantt
Double-click a bar in the Gantt (or click the pencil in the grid) and open Purchase Orders:
- The slab pour is linked to Delivery 2, which is confirmed...
- ...and to Overrun 1, which hasn't been ordered yet.
- All deliveries and the tick boxes work as on the job screen.
- Delivery 1 belongs to the piers and footings task.
- Unlike the Checklists tab, changes here are saved when you click Save.
Without Estimating, the Purchase Orders tab still appears, but it stays empty.
Questions and tips
If I re-send an order, does the task keep its link?
Yes. Links follow the delivery, so the task shows the new PO number and status.
What does Order changed mean?
The delivery it was linked to is no longer on the estimate: it was deleted, or moved to another supplier or delivery number. Remove the link and link the current order.
Can two tasks point to the same order?
Yes, for example a delivery task and an install task. Both show the order, and each says what else it's linked to.
Can a job with several estimates link orders from any of them?
Yes. The job's Purchase Orders screen lists orders from all the job's estimates, with a filter to pick one.
Need a hand? Contact our support team.