The job's Gantt shows the same tasks as the Checklists tab, as bars on a calendar with the links between them. Whatever you change in one shows in the other. Drag a task and everything that follows it moves with it, skipping days off.
Our example (all names and details are made up): the checklist Construction Schedule - 2 Storey has 37 tasks from site cut to handover. It runs on job #2041, 17 Banjo Street, a two storey home for Mia and Josh. Sam, the site supervisor, runs the schedule and calls up the trades.
On this page
- Open the Scheduling tab
- Read the bars
- Move a task
- Make a task longer or shorter
- Link tasks
- Edit a task
- Add or delete tasks
- Rearrange, Undo and Lock
- Actual, Projected and Both
- Calendar and List views, and printing
- Questions and tips
Open the Scheduling tab
Open the job and go to the Scheduling tab.
- Switch between Calendar, List and Gantt views.
- Actual (where work really is), Projected (the plan) or Both.
- Add Checklist: add another checklist to the job from here.
- Rearrange: re-apply the links and days off to every task.
- Undo / Redo the last date changes (Ctrl+Z / Ctrl+Y).
- Expand or collapse all, zoom in and out, zoom to fit, and step the timeline back and forward.
- Today scrolls to today.
- The menu at the end has Print, Lock and display settings. On a wide screen they show as buttons, with a Find tasks by name box.
- Today's date and time. Shaded columns are days off.
The grid on the left shows each task's Assignee (click to change), Start Date and End Date. Scroll it right for Duration, Progress, linked purchase orders (the POs column; without Estimating it stays empty; see Managing linked purchase orders on a job and Gantt), when it was Sent, and an Email button that works just like the one on the Checklists tab, using the dates on the Gantt.
Read the bars
- Each bar runs from the task's start to its finish, in the task's colour.
- The darker part of a bar is the work done. Roofer - Roof on is part-way through.
- Arrows are the links. A task's arrow comes from the task it follows.
- Hover over a bar for its start, end, working days and % complete.
Move a task, and everything after it follows
Tall Timber Carpentry ring: they can't start the lock-up until Tuesday. Sam drags Carpenter - Lock-up (1) one day to the right.
After the move, the frame inspection, the three rough-ins, insulation and plastering (2) all move with it. The rough-ins now finish on Monday because the weekend is skipped.
How moving works:
- A task keeps its working days when you drag it, and it never lands on a day off.
- The tasks that follow it are placed by their links, so they move later (or earlier) with it.
- Completed tasks never move by themselves.
- Dragging a task further from the one it follows leaves a gap: that gap becomes its wait (lag) and is kept.
- Changed your mind? Undo (Ctrl+Z) puts the dates back.
- The trades' call-ups aren't re-sent automatically. Use Resend so they have the new dates (see Calling up trades from a checklist).
Make a task longer or shorter
Drag either end of a bar to change when it starts or finishes, or change Working Days in the task editor. The tasks that follow move to match. Drag the small handle inside a bar to set its % complete: reaching 100% completes it.
Link tasks
Hover over a bar and drag from the circle at its end onto the bar of the task that should follow. Click an arrow to edit or delete the link:
- Type: keep Finish to Start. It's the type the schedule follows.
- Lag: extra working days to wait. 0 is the next working day, the same as Start After # Days.
A task with links from several tasks waits for the last of them to finish.
Edit a task
Double-click a bar, or click the pencil in the grid.
| General | Name, Assignee, Email Task (alert the assignee when you save), Mark as important, % complete, Working Days, Start and Colour. Finish and Duration are worked out for you. |
| Todos | Quick to-dos on the task, with a due date and who. |
| Predecessors / Successors | The task's links, with their lag. |
| Purchase Orders | Link the orders for this work (Pro and Studio plans, with Estimating). Without Estimating the tab still appears, but it stays empty. See Managing linked purchase orders on a job and Gantt. |
| Invoices | Link supplier invoices. |
| Files | Upload a file, or link one from the job's files. |
Click Save. Clicking a checklist's own row (the bar across the top) lets you change the assignee for all its tasks at once.
Add or delete tasks
- The + at the end of a row adds a task straight after it.
- Right-click a checklist's row for Add Task, Edit checklist… or Delete task (deleting a checklist row removes the whole checklist from the job).
- Right-click a task for Edit or Delete task. Deleting can't be undone.
- New tasks start today, one day long, with no links: drag them into place and link them.
Rearrange, Undo and Lock
- The notice only appears when you open the Gantt and some tasks aren't where their links put them (for example after a date was changed on the Checklists tab). It does not appear when you drag a bar: dragging already moves the linked tasks with it. The notice looks like: "1 task doesn't line up with the tasks they follow (start after, gaps, days off). Nothing has been changed." Nothing is changed until you choose Update dates (on the right of the notice); Keep as is leaves them.
- Rearrange does the same for the whole job at any time: every unfinished task is placed by its links and days off.
- Undo goes back up to 10 date changes since you opened the page.
- Lock stops tasks being dragged or edited on your computer, so you can scroll and zoom without moving anything by accident. Click it again to unlock.
Actual, Projected and Both
Actual shows when work really started and finished (once ticked), Projected shows the plan, and Both (1) shows the actual bars with the plan as a dashed outline, so you can see what ran late. Here the slab pour (2) happened a day after it was planned and the lower frame (3) started late and ran over. Both is for looking only: switch back to Actual or Projected to make changes.
Calendar and List views, and printing
Calendar shows the month with each task across its days; click a task to edit it, or double-click a day to add one. List shows the tasks as a simple table with their dates and an Email button.
Print opens a Print settings window. Month is a dropdown: All months prints the whole chart, or you can pick one month that has work. You can also choose the checklist (if the job has more than one), paper size (A4 or A3), orientation, row height and how wide the task names are. Handy for the site shed.
Questions and tips
Why did a task jump past a weekend or a public holiday?
Tasks never start on a day off. Weekends (when ticked), public holidays and off-days in your business calendar are skipped, and a task's working days don't count them.
I can't drag anything.
Check you're not in Both view, and that Lock isn't on.
The Gantt says tasks don't line up.
This notice appears when you open the Gantt and some tasks aren't where their links put them, for example after a date was changed on the Checklists tab. Dragging a bar on the Gantt moves the linked tasks along and never shows the notice. Choose Update dates to place them by their links, or Keep as is to leave them. Rearrange does the same any time.
How do I delete a task?
Right-click it and choose Delete task. This can't be undone.